Missouri Furnace Co. v. Cochran
8 F. 463 (W.D. Pa. 1881)
Facts
Missouri (P) entered into a contract with Cochran (D) for the delivery of 36,621 tons of coke at $1.20 per ton. deliverable at the rate of nine cars of 13 tons per day. After about 4,000 tons were delivered, D notified P that he was rescinding the contract. P then made a contract with Hutchinson for the delivery of the 29,587 tons at a price of $4 per ton. P sued for the difference in price between the $4 and $1.20 price agreed upon. The trial court refused to instruct the jury on anything but the market price difference as the measure of damages from which the jury awarded $22,171.49. P moved for a new trial.
Nature Of The Case
This section contains the nature of the case and procedural background.
Issues
The legal issues presented in this case will be displayed here.
Holding & Decision
The court's holding and decision will be displayed here.
Legal Analysis
Legal analysis from Dean's Law Dictionary will be displayed here.