Eker Brothers, Inc. v. Rehders

150 N.M. 542 (2011)

Free access to 20,000 Casebriefs

Issues

The legal issues presented in this case will be displayed here.

Nature Of The Case

This section contains the nature of the case and procedural background.

Facts

P submitted a bid to Rehders (D), general contractor, to perform site and concrete work necessary to construct an elementary school. P agreed to reduce the site work bid by $100,000. D verbally accepted the bid and work began on the project. D paid P's first invoice, covering work from July 1 to July 31, in full. P continued work through August, and on September 2, Subcontractor tendered an invoice for $126,358.95 covering work performed between August 1 and August 31. On September 8, P ceased all work on the project. Four days later, on September 12, d offered to pay $58,947.95 for the work Subcontractor had performed. P did not accept this payment. On September 14, P submitted an invoice for the work it had performed from August 1 to September 7 in the amount of $122,099.45. D did not pay. P sued D. The district court concluded that the value of the work performed by P between August 1 and September 7 and invoiced on September 14 was $74,964.05. It found that D had 'incurred an extra $ 50,194.45 in additional expenses due to P's failure to complete the concrete work.' It also found that General had mitigated its damages by completing the site work for $7,746.25 less than it would have paid P. The court concluded that D's damages were $ 42,448.20. The district court did not offset the amount owed to P against the damages but instead entered judgment against P for the full amount of the damages. P appealed.

Holding & Decision

The court's holding and decision will be displayed here.

Legal Analysis

Legal analysis from Dean's Law Dictionary will be displayed here.

© 2007-2025 ABN Study Partner

© 2025 Casebriefsco.com. All Rights Reserved.