Brian Construction And Development Co. v. Brighenti,
176 Conn. 162, 405 A.2d 72 (1978)
Facts
Brian Construction (P) was assigned a contract to build a post office. P then entered into a contract with Brighenti (D) who agreed to perform all excavation, grading, site work, asphalt pavement, landscaping, and concrete work for $104,326 and to do everything necessary and requisite for the completion of these duties. D commenced the work and soon discovered considerable debris below the surface; this was not reflected in the test borings for the excavation. The cost of the removal of this rubble was not included in the plans. P then notified the architect for the owner, but the owner would not give written authorization for the removal of the debris. D then ceased work on the site and notified P and offered to complete the work if P were to remove the debris. Then P and D entered into an oral agreement to remove the rubble at cost plus 10%. D began work again but abandoned the cite when P refused to confirm the transaction in writing. P completed the contract. P sued. Judgment was given to D on P’s claims and for P on D's counterclaim. P appealed.
Nature Of The Case
This section contains the nature of the case and procedural background.
Issues
The legal issues presented in this case will be displayed here.
Holding & Decision
The court's holding and decision will be displayed here.
Legal Analysis
Legal analysis from Dean's Law Dictionary will be displayed here.
© 2007-2025 ABN Study Partner